EMC E20-012 is a qualifying exam for the EMC Storage Technologist Specialist track.
For example:
1. A company has a shared prestaged infrastructure at an alternate site. This enables the company to ebuild systems and applications in the event of a disaster. What is the term for this alternate site trategy?
A.Automated failover site
B.Cold site
C.Hot site
D.Warm site
Answer: C
2. A company has developed a Disaster Recovery plan that includes:
A. Computer Equipment List
B. List of phone numbers of key people in company
C. Failover procedure for synchronous replication
Which additional item should be included in the Disaster Recovery plan?
A.Business Impact Analysis report
B.Disaster recovery test results from the last three tests
C.Fault Tree Analysis report
D.Location of the recovery facility
Answer: D